A double-wide or other multi-section home leaves the factory in pieces and is finished at the lot. This guide explains what the Texas rules say about joining the sections, sealing the seam and connecting the ducts, water, drain, wiring and gas between them, so you know what to ask the installer.
By West Ranch, Stephenville, TX. Published November 23, 2026.
The short answer
A multi-section home is set on its piers one section at a time. The installer then fastens the floors, end walls and roof together, seals the seam, and connects the systems that cross between the sections. The state publishes generic standards for each of those steps in 10 Texas Administrative Code §80.25. A new home is installed to the manufacturer’s approved instructions, so ask which set the installer is following.
Sealing the mating line
The mating line is the seam where two sections meet along the floor, end wall and ceiling. Before the next section is positioned, the seam needs material or a method that limits air leakage and water vapor movement. The standards allow three:
- Expanding foam along surfaces that can still be reached after the sections are joined.
- Caulking along surfaces that can still be reached after the sections are joined.
- A non-porous gasket along the perimeter of all mating lines.
Where the walls line up between sections, non-porous material has to go in before the units are joined. Insulation, carpet, carpet pad and other porous materials are not acceptable for this job.
Floors, end walls and roof
- Floors: gaps up to 1-1/2 inches that do not run the full length of the floor can be filled with lumber, plywood or other suitable shims. Gaps under 1/2 inch do not need shimming. The floor assemblies must be fastened together, and any tear in the bottom board from a fastener has to be repaired.
- End walls: fastened at the mating line with at least #8 by 4 inch wood screws or 16d nails at no more than 8 inches on center, or 5/16 lag screws at no more than 12 inches on center, with at least 1-1/2 inches of penetration into the opposite end wall stud.
- Roof:connected with the fasteners and spacings in the state’s figure. Fasteners must not be used to pull the sections together. Roof gaps up to 1-1/2 inches that do not run the full length can be shimmed, and gaps up to 1/2 inch do not need it.
- Roof close-up: shingles go to the edge of the decking at the peak. At least a 6 inch wide strip of 30 gauge galvanized flashing runs the length of the roof under the ridge cap, lapped 6 inches where it is not continuous. Wind Zone II (high wind) installations need additional fasteners.
Ducts, water, drain and wiring between the sections
- Heating and cooling duct: the crossover duct must be listed for exterior use, have an insulation value of at least R-4, be supported at no more than 48 inch intervals, and must not touch the ground.
- Water: where water service reaches another section, the crossover lines are connected. Exposed lines outside the insulated floor are wrapped or boxed in insulation. If the water pipe at the inlet is exposed, heat tape listed for manufactured home use should be installed to prevent freezing.
- Drain, waste and vent: parts of this system under the floor are often left unassembled for transport. Pipe of 3 inches or larger needs at least 1/8 inch of slope per foot, smaller pipe at least 1/4 inch. Direction changes use long sweep fittings, drain piping is supported at no more than 4 foot intervals, and a cleanout goes at the upper end of the floor piping.
- Electrical: crossover wiring is a plug-in type, junction boxes inside the floor cavity, or a single-circuit pigtail in a junction box. Crossover wiring outside the floor cavity must be in conduit. Each chassis is bonded to the next with a number 8 copper conductor, or a 4 inch wide 30 gauge metal strap as an alternate. A licensed electrician is required to run the feeder from the pole to the main panel box.
- Fuel gas:underfloor crossover connections must be accessible and made with the manufacturer’s connectors or listed flexible connectors with a quick disconnect or shut-off valve.
What gets tested
The rule requires the water system and the drain system to be inspected and tested for leaks at the site after the work is complete. When the water heater is disconnected, an air-only test may be used on the water system. The gas piping gets an air pressure test of no less than 6 and no more than 8 ounces, and the appliance and crossover connections are checked with soapy water or bubble solution while the line is pressurized. The person connecting the gas supply is responsible for that test, and the gas utility or supplier may also perform it.
The space under the home
If a used home is installed to the state’s generic standards and the retailer or installer provides the skirting, the enclosure has to meet §80.22. That means at least one tool-free access opening no smaller than 18 inches in any dimension and 3 square feet in area, six screened vents (one at each end and two on each side) with ventilation of 1 square foot of net free area per 150 square feet of floor area, and a ground vapor retarder of 6 mil polyethylene sheeting overlapped about 12 inches at the joints. For footings, piers and anchors, see foundations, piers and tie-downs for a manufactured home in Texas.
Questions to ask before the sections are joined
- Which instructions is the home being set to, the manufacturer’s or the state’s generic standards?
- How is the mating line sealed, and with what material?
- Who connects and tests the water, drain and gas, and can I see the results?
- Who runs the electrical feeder, and is that person a licensed electrician?
- How are the ducts supported so they stay off the ground?
- Who does the skirting and ground vapor control, and when?
- Can I see the installer’s compliance checklist and Form T afterward?
Where West Ranch fits
West Ranch in Stephenville sells new manufactured homes and leases the lot under each one. To ask how a specific home is set, or to see the installation papers for it, call (254) 977-8968 or use the contact page. The general installation steps are in how a manufactured home is installed in Texas, and the size differences between one and two sections are in single-wide vs double-wide. This guide is general information and not engineering or legal advice.
Frequently asked questions
How are the two halves of a double-wide joined on site?
- The floors, end walls and roof of the sections are fastened together along the mating line, and the seam is sealed against air and water vapor with foam, caulk or a non-porous gasket. Ducts, water lines, drain pipes, wiring and any gas piping that cross between the sections are then connected and tested.
What is the mating line?
- It is the seam where two sections of a multi-section home meet along the floor, end wall and ceiling. Before the second section is positioned, the state's generic standards call for material or procedures that limit air leakage and water vapor movement across it.
Can insulation or carpet be used to seal the seam?
- No. The state's generic standards say insulation, carpet, carpet pad and other porous materials are not acceptable for sealing the mating line.
What gets tested after the sections are joined?
- The water system and the drain system must each be inspected and tested for leaks at the site after the work is complete. A fuel gas system gets an air pressure test of 6 to 8 ounces, with a soapy-water check of the appliance and crossover connections.
Who runs the electrical feeder to the home?
- The state's generic standards say a licensed electrician is required to run the feeder from the pole to the main panel box in the home. The standards also call for each chassis to be bonded to the next one with a number 8 copper conductor or an approved metal strap.
Do these rules apply to every home?
- A new home is installed by a licensed installer following the home manufacturer's approved installation instructions. The state's generic standards are the published fallback for used homes and for details the manufacturer's instructions do not cover, so ask the installer which instructions the home is being set to.
Sources
- TDHCA: Manufactured Housing federal and state laws and rules
- 10 Tex. Admin. Code § 80.21: Requirements for the Installation of Manufactured Homes
- 10 Tex. Admin. Code § 80.22: Generic Standards for Moisture and Ground Vapor Controls
- 10 Tex. Admin. Code § 80.25: Generic Standards for Multi-Section Connections Standards
- TDHCA: Installer Forms and Information
General information, not legal or financial advice. Rules and programs change; check the linked sources and ask your lender or a Texas attorney about your own situation.
See West Ranch
More guides
- Manufactured, mobile and modular homes: what is the difference?
- Single-wide vs double-wide manufactured homes
- Land-lease community vs buying your own land
- Manufactured home financing in Texas
- Buying a manufactured home in Texas, step by step
- Moving to Stephenville, TX
- Housing near Tarleton State University
- HUD label, data plate and Statement of Ownership in Texas
- How a manufactured home is installed in Texas
- Foundations, piers and tie-downs for a manufactured home in Texas
- Manufactured home: real property or personal property in Texas
- Moving a manufactured home in Texas: permit, installer and paperwork
- Selling a manufactured home in Texas: do you need a retailer license?